North East Lincolnshire Council

Public Notice of Temporary Prohibition of Traffic Order – 14 March 2019

THE BOROUGH OF NORTH EAST LINCOLNSHIRE

THE NORTH EAST LINCOLNSHIRE BOROUGH COUNCIL
(A SECTION OF A18, BARTON STREET, GRIMSBY – TTRO 19-039)
(TEMPORARY PROHIBITION OF TRAFFIC) ORDER 2019

NOTICE IS HEREBY GIVEN that the North East Lincolnshire Borough Council intends to make, not less than seven days from the date of this Notice, an Order, the effect of which will be to prohibit any vehicle, pedestrian or cycle from proceeding along the below sections of highway between 07:00hrs and 18:00hrs from Monday 1st April to 11th April 2019, the extents of which are:

A18 Barton Street –     Phase 1 – from its junction with Laceby Road ‘Oaklands’ Roundabout to its junction with Waltham Road

Phase 2 – from its junction with Waltham Road junction to its junction with Thoroughfare

Phase 3 – from its junction with Thoroughfare to its termination at the boundary with East Lindsey District Council

This temporary prohibition is required in order to safely facilitate essential maintenance works.  The dates and times above are correct at the point of print however should adverse weather or any other conditions impact the works they will go ahead when it is safe to do so.  Diversion routes will be signposted and published online at: www.roadworks.org and https://www.nelincs.gov.uk/category/public-notice/.

The Order will come into operation on Monday 1st April 2019, and will continue in force for a period not exceeding eighteen months unless extended for a further period by the Secretary of State for Transport, or until completion of the works (whichever is the earlier). The road will be reopened as soon as possible.

A copy of the sealed Order may be inspected online at the Municipal Offices, Town Hall Square, Grimsby during normal office hours. For further information you may, if you wish, telephone NELC Highways Design (01472 324167) for an explanation of the proposals.

Dated this 14th day of March, 2019

Rob G. Walsh
Chief Executive

Municipal Offices
Town Hall Square
Grimsby
DN31 1HU

Plans:

TTRO 19-039 – Closure Phasing Plan