CONCRETE pours are due to take place on the A180 today (Friday, 6 November) as the major scheme to maintain and protect the highway’s two flyovers and one bridge enters its final stage.
Works were ongoing yesterday to ensure the ‘forming’ was in place to allow for the pour, with drilling and surveying also undertaken.
As reported earlier this week, solid concrete pads with steel bars inside are needed to hold the central barriers being put in where the work is taking place along the A180.
Motorists will then notice the work will be left until Monday (9 November) to allow the concrete to set – it needs 48 hours – ahead of the barrier installation and Vehicle Restraint Systems (VRS) work. VRS is a term for the infrastructure needed to ensure that motorists can travel safely.
Once this is all done, the major scheme will be complete with both sides of the road fully open. This work has involved significant maintenance to Gilbey Road and Cleethorpe Road Flyovers and Alexandra Dock bridge.
Supported by £8-million awarded by the Department for Transport, the scheme was vital to ensure the long-term future of the structures, which when fully open carry up to 27,000 vehicles every day to and from Grimsby and Cleethorpes. Structural surveys had identified deterioration that needed addressing. Failure to act was likely to lead to serious problems in the decade ahead.