Corporation Road Bridge update: Footpath closures and weekend working in January 2024

11:07 am, Wednesday, 20th December 2023 - 4 months ago

General

Additional repair survey works are currently being carried out on Corporation Bridge and mechanical repair works are progressing above deck.

To continue the mechanical preparation works to the underdeck of the bridge, weekend working is required due to expected low tidal levels. Footpath closures are needed whilst works are undertaken adjacent to public areas to ensure the safety of both the public and the contractor.

Footpath closures will take place between 9am and 4pm.

The footpath will remain open during the weekend working dates.

January 2024 weekend working and footpath closure dates:

  • Thursday 4 January – footpath closure
  • Saturday 6 January – weekend working
  • Sunday 7 January – weekend working
  • Tuesday 9 January – footpath closure
  • Wednesday 17 January – footpath closure
  • Saturday 20 January – weekend working
  • Sunday 21 January – weekend working
  • Tuesday 23 January – footpath closure
  • Tuesday 30 January – footpath closure

North East Lincolnshire Council, its delivery partner, Equans and contractor Spencer Group would like to thank the public for their patience whilst the work is being undertaken.

Visit www.investnel.co.uk/corporation-bridge to keep up to date with the Corporation Road Bridge works.

Next Article
Go wild in May and give nature the chance to thrive
If you’re a gardener with a lawn like Wembley then the thought of not mowing your lawn for a whole month probably fills you with terror. But spare a thought for the wildlife whose habitats are disturbed every time you run the lawn-mower around the garden. No Mow May was introduced to give nature the...