Works to Grade II listed structure, Corporation Road Bridge, have been progressing.
Work is also continuing to the bridge’s decks with lifting span and reinforced concrete deck designs being finalised.
To take advantage of anticipated low tide levels, weekend working is required. Footpath closures are also required whilst works are taking place adjacent to public areas to ensure the safety of both the public and the contractor.
Footpath closures will take place between 9am and 4pm each weekday. The footway will remain open during the weekend working dates. Temporary signs will be in place for the footway closures.
October 2024 weekend working and footway closure dates
South Footpath Closures
- Wednesday 2 October
- Thursday 3 October
- Tuesday 8 October
- Wednesday 16 October
- Thursday 17 October
- Tuesday 22 October
- Wednesday 30 October
- Thursday 31 October
Weekend Working
- Saturday 12 October and Sunday 13 October
- Saturday 26 October and Sunday 27 October
North East Lincolnshire Council, its delivery partner, Equans and contractor Spencer Group would like to thank the public for their patience whilst the work is being undertaken. As Corporation Road Bridge is a construction site, it is important that the public respect the access restrictions in place, which have been introduced for safety reasons. Members of the public are reminded to please stay outside of all encapsulated and other working areas for their own safety, as well as that of those working there.
Visit InvestNEL (InvestNEL | Corporation Road Bridge Major Restoration – InvestNEL) to keep up to date with the Corporation Road Bridge works.
Share this article