Skip to main content

Corporation Road Bridge Update: Footway closures and weekend working in April 2025

9:42 am, Tuesday, 1st April 2025 - 4 weeks ago

Bridges

Works to Grade II listed structure, Corporation Road Bridge, have been progressing, with grit blasting and painting works continuing to Spans 5 and 6.

The Northern footway has been waterproofed and is about to be surfaced to allow the switching of works to the opposite side. This switch is expected during the week commencing 31 March 2025.

As this work is undertaken, the pedestrian footway will switch from the South side of the bridge to the North side.

A final footway treatment will be added later in the works.

To take advantage of anticipated low tide levels, weekend working will also continue to take place next month.

Footway closures are also required whilst works are taking place adjacent to public areas to ensure the safety of both the public and the workers on site.

To help complete remaining sections of the works the footway may be closed for 1 or 2 days a week if conditions allow.

Footway closures will take place between 9am and 4pm each weekday as detailed below. The footway will remain open during the weekend working dates. Temporary signs will be in place for the footway closures.

March 2025 weekend working and footway closure dates:

South Footway Closures

  • Tuesday 1 April
  • Wednesday 2 April (provisional)
  • Wednesday 9 April
  • Wednesday 16 April
  • Wednesday 23 April
  • Wednesday 30 April

Weekend working

  • Saturday 5 April and Sunday 6 April
  • Saturday 19 April and Sunday 20 April

North East Lincolnshire Council, its delivery partner, Equans, and contractor, Spencer Group, would like to thank the public for their patience whilst the work is being undertaken.

As Corporation Road Bridge is a construction site, it is important that the public respect the access restrictions in place, which have been introduced for safety reasons. Members of the public are reminded to please stay outside of all encapsulated and other working areas for their own safety, as well as that of those working there.

Visit https://investnel.co.uk/grimsby-developments/corporation-road-bridge-refurbishment-scheme/ to keep up to date with the Corporation Road Bridge works.

Next Article
Corporation Road Bridge Update: Footway closures and weekend working in March 2025
Complex engineering work continues to grade II listed structure, Corporation Bridge. Grit blasting continues to Span 5 and 6, alongside priming, chipping of excessive corrosion and substructure repair works. Control...

Share this article