North East Lincolnshire Council and its delivery partner, Equans, will be carrying out essential planned maintenance on Kiln Lane between North Moss Lane and Kiln Lane level crossing, Stallingborough.
Works will begin on Monday 23 September and will be completed on Thursday 14 November.
The works will be carried out in two phases, as detailed below:
Phase 1 – Civil works (Monday 23 September – Saturday 02 November)
The first phase of the works will include the replacement of existing damaged kerbs, channels and drainage works. These works will be carried out 24 hours a day, 7 days a week, under the following traffic management arrangements:
Phase 1A – North Moss Lane to Netherlands Way: All civil works within this section of Kiln Lane will be carried out under temporary traffic control.
Phase 1B – Netherlands Way to Europa Way: All civil works within this section of Kiln Lane will be carried out under a lane closure with a right turn ban for vehicles turning right into businesses from Kiln Lane. To ensure access to businesses remains available, all vehicles must turn left into and out of businesses along this section of Kiln Lane whilst the works take place. Vehicles will be directed to turn around at the roundabouts at either end of Kiln Lane.
Phase 1C – Europa Way to Kiln Lane level crossing: All civil works within this section of Kiln Lane will be carried out under lane closure up to the last business entrance before the level crossing. A full road closure will also be in place from the last business entrance over the level crossing up to Hobson Way roundabout. There will be no vehicular access to Kiln Lane from Hobson Way or Laporte Road.
Phase 2 – Carriageway reconstruction and road marking (Wednesday 23 October – Thursday 14 November)
The second phase of the project is carriageway reconstruction and road marking work, which will start on Wednesday 23 October and is scheduled to be completed on Saturday 16 November.
To enable the works to be carried out, and to ensure the safety of the contractors, a night time road closure will be in place each night between 7pm and 6am. To minimise disruption the work has been split into two sections:
Section 2A – Between North Moss Lane Roundabout and Kia Motors Entrance
Dates of overnight road closures as below:
- Wednesday 23 October 2024
- Thursday 24 October 2024
- Friday 25 October 2024
- Monday 28 October 2024
- Tuesday 29 October 2024
- Wednesday 06 November 2024
- Thursday 07 November 2024
- Friday 08 November 2024
Section 2B – Between Kia Motors Entrance and Kiln Lane Level Crossing
Dates of overnight road closure as below:
- Wednesday 30 October 2024
- Thursday 31 October 2024
- Friday 01 November 2024
- Monday 04 November 2024
- Tuesday 05 November 2024
- Monday 11 November 2024
- Tuesday 12 November 2024
- Wednesday 13 November 2024
There will be no vehicle access within the road closure extents, and on street parking will also be suspended. Please be aware that these works are weather dependent and are subject to change.
Access for emergency vehicles will be maintained throughout the works.