North East Lincolnshire Council wants to inform of civil works and carriageway resurfacing on Pelham Road between Kings Road and Worsley Road, Immingham.
These works will begin on Monday 30 June 2025 for six weeks and should be completed on Friday 8 August 2025.
The works will be carried out in three phases as detailed below:
Phase 1 – Civil works (Monday 30 June – Monday 28 July)
The first phase of the works will include the replacement of existing damaged kerbs, channels, tactile paving, and a section of footway reconstruction between the zebra crossing and the County Hotel. These will be carried out under temporary traffic signals during the day between 7:30am and 6pm.
All works on Humberville Road in front of the County Hotel will be carried out under a one-way system from Pelham Road towards Humberville Road. During this period, all parking on this section of Humberville Road will be suspended.
From Monday 7 July to Sunday 13 July, the bus stop outside County Hotel will be closed, but the bus stop opposite the County Hotel will be available for use as normal. From Wednesday 16 July to Sunday 20 July, the bus stops outside and opposite the Pilgrim Primary Care Centre will be closed.
Phase 2 – Carriageway resurfacing works (Monday 28 July – Wednesday 6 August)
This work will include the replacement/adjustment of utility covers on carriageway and carriageway resurfacing and be carried out under full nighttime closure between 7pm and 6am in four sections:
Section 1: King’s Road to 16 Pelham Road
Full road closure on Thursday 31 July and Friday 1 August between 7pm and 6am.
Section 2: 16 Pelham Road to Zebra crossing at Humberville Road junction
Full road closure on Wednesday 30 July and Monday 4 August between 7pm and 6am.
Section 3: Zebra crossing near Humberville Road to Golden Garden Takeaway, including section of Humberville Road in front of the County Hotel
Full road closure on Tuesday 29 July and Tuesday 5 August between 7pm and 6am.
Section 4: Golden Garden Takeaway to 30m west of Worsley Road Junction
Full road closure on Monday 28 July and Wednesday 6 August between 7pm and 6am.
The bus stops outside and opposite the County Hotel will be closed between 7pm and 6am on the following nights: Tuesday 29 July and Tuesday 5 August. The bus stops outside and opposite the Pilgrim Primary Care will be closed between 7pm and 6am on the following nights: Monday 28 July and Wednesday 6 August.
Please be aware that no vehicle access will be permitted within the road closures for the duration of the works, but footway access will be maintained.
Phase 3 – Road markings (Thursday 7 August – Friday 8 August)
These works will be carried out under a full nighttime road closure between King’s Road and Worsley Road on Thursday 7 August and Friday 8 August between 7pm and 6am. Resident access will be provided under marshal control.
All bus stops on Pelham Road between King’s Road and Worsley Road will be closed between 7pm and 6am on Thursday 7 August and Friday 8 August.
During the works, on street parking and loading will be suspended within the closures. If the works are delayed due to parked vehicles, additional nights of road closures will be required to enable the works to be completed. Please be aware that these works are weather dependent and are subject to change.
Access for emergency vehicles will be maintained throughout the works.
The council, and contractor EC Surfacing Ltd, would like to apologise in advance for any inconvenience and assure you that the work will be completed as quickly and safely as possible. We would like to take this opportunity to thank you in advance for your patience and co-operation during these important upgrade works.