Real Time Information displays – installation works update

1:42 pm, Wednesday, 26th August 2020 - 4 years ago

General

Works to install eight new Real Time Information (RTI) displays at additional locations in North East Lincolnshire will now be complete by Friday 4 September.

The works initially started on Monday 10 August, on a rolling programme, along Scartho Road and Cromwell Road, Grimsby.

All locations were due to be complete by Friday 21 August, but due to complications with the existing infrastructure of some of the proposed locations, work has been delayed. As a result of this, works will now be complete by Friday 4 September.

RTI screens provide bus passengers with the latest journey information, advising on when they can expect their next bus to arrive, with the aim to improve information provided at bus stops and make public transport more accessible.

To avoid disruption to residents and keep the workforce safe, localised traffic management (cones and barriers) will be in place on the footpath whilst works take place. There will be no impact to the highway network.

The project is being managed and overseen by the council’s regeneration partner, ENGIE, with McCann Ltd installing the fixtures, and R2P connecting the screens.

The council, ENGIE and McCann Ltd would like to apologise for any disturbance caused.

If you require more information, please contact the team on (01472) 325670.

Alternatively, visit www.nelincs.gov.uk/roadworks for the latest live travel information in the area, including congestion and roadworks.

Next Article
A180 Bridge repair scheme: Meet the contractor drop in events
The A180 Bridge repair scheme is underway, with work currently ongoing at Gilbey Road Bridge, between Westgate Roundabout and Pyewipe Roundabout as well as the underside of Cleethorpe Road bridge. As part of the works, the contractors, VSL, are holding “Cuppa with the Contractors” drop in sessions to explain about the works and answer any...