Skip to main content

Resurfacing works planned for Grimsby road

10:34 am, Monday, 3rd March 2025 - 2 months ago

Highways

T Balfe Construction on behalf of Allison Homes will be carrying out works on Blyth Way, Laceby.

The first phase of works will consist of road planning to remove the surface layer of tarmac. This will take place between Marigold Road and Arnold Close on Friday 28 February.

Footway and carriageway resurfacing will then take place in same location between Thursday 6 March and Friday 7 March. Full access will be maintained by temporary signals during these works.

A shorter section of temporary signals will follow at Marigold Road from Tuesday 11 March to Friday 28 March.

For more information, please contact T Balfe Construction on 03700 500 792.

Next Article
Bus stops to be suspended on night of Mayoral election
A number of bus stops are set to be suspended on the night of the Mayoral election. The count for the Mayor of the Greater Lincolnshire Combined County Authority (GLCCA)...

Share this article