Skip to main content

Resurfacing works planned for Grimsby road

10:34 am, Monday, 3rd March 2025 - 4 months ago

Highways

T Balfe Construction on behalf of Allison Homes will be carrying out works on Blyth Way, Laceby.

The first phase of works will consist of road planning to remove the surface layer of tarmac. This will take place between Marigold Road and Arnold Close on Friday 28 February.

Footway and carriageway resurfacing will then take place in same location between Thursday 6 March and Friday 7 March. Full access will be maintained by temporary signals during these works.

A shorter section of temporary signals will follow at Marigold Road from Tuesday 11 March to Friday 28 March.

For more information, please contact T Balfe Construction on 03700 500 792.

Next Article
UPDATE: Essential work on North Prom coming this week
Work continues on the installation of a brand new free footwash, funded by TransPennine Express, on North Prom ahead of the summer season. The footwash design has been created by...

Share this article