Skip to main content

Ward parish funding schemes in August

11:51 am, Monday, 8th August 2022 - 2 years ago

General

North East Lincolnshire Council and its regeneration partner, EQUANS, will be delivering a variety of works across the borough. These works are part of the Local Transport Plan scheme.

The works will be carried out across four different site locations between 7:30am and 6pm.

Indicative programme of works:

Phase 1 – Immingham Road, Habrough – Monday 15 August

The first phase of works will take place on B1210 Immingham Road between no.4 and up to the junction of Mill Lane, Immingham. The works include the provision of new road markings and marker posts, as well as the upgrade and replacement of an existing traffic sign.

The works are programmed to start on Monday 15 August and will take approximately two days to complete. During this time, the road will be under two-way temporary traffic signals and mobile traffic management (stop and go boards).

Phase 2 – Aylesby Village – Monday 15 August

The second phase of works will take place in Aylesby Village on the full length of Beach Holt Lane and Nooking Lane and up to the junction of Butt Lane on Main Road in Laceby. The works include new road markings, refreshing the existing markings and upgrading the existing traffic signs.

The works are programmed to start on Monday 15 August and will take approximately two days to complete. During this time, there will be a full road closure on Beach Holt Lane, Nooking Lane and Main Road (up to the junction of Butt Lane) and a signed diversion route will be in place.

Phase 3 – Butt Lane, Laceby – Wednesday 17 August

The third phase of works will take place on Butt Lane, between the mini roundabout at Little Beck / Mulberry Lane and up to the Londmeadows Drive junction in Laceby. The works include the provision of new road markings and replacement of existing traffic signs.

The works are programmed to start on Wednesday 17 August and will take approximately two days to complete. During this time, the road will be under two-way temporary traffic signals and mobile traffic management (stop and go boards).

Phase 4 – Ashby cum Fenby – Wednesday 17 August

The fourth phase of works will take place in Ashby cum Fenby on the full length of Ashby Lane and Main Road (up to the junction of Post Office Lane). The works are programmed to start on Wednesday 17 August and will take approximately two days to complete.

The works include the provision of new road markings, refreshing the existing markings and upgrading the existing traffic signs. During this time, there will be a road closure on Ashby Lane and Main Road (up to the junction with Post Office Lane) and a signed diversion route will be in place.

Please note, the contractors can only provide an approximate programme of works due to being the uncertainty of exact timescales required at each location, as well as the works being subject to weather permitting conditions. Therefore, as a contingency, there may be works on Friday 19 August.

Advanced warning signs will be put up on-site closer to the time.

The council, EQUANS and contractors Riggotts & Co Ltd and J McCann & Co Ltd, would like to apologise in advance for any inconvenience this may cause.

Next Article
Mermaid Café building’s bright new future
150 years ago, in 1874, the Mermaid Café building on Cleethorpes North Prom sea front was constructed as a waiting room for the recently opened Manchester, Sheffield and Lincolnshire Railway. ...

Share this article