ROAD TRAFFIC REGULATION ACT 1984 – SECTION 14(1)(a)
THE NORTH EAST LINCOLNSHIRE BOROUGH COUNCIL
NOTICE IS HEREBY GIVEN that the North East Lincolnshire Borough Council have made, an Order, the effect of which will be that no person shall cause or permit any motor vehicle from proceeding along the below sections of highway:
WATERSIDE DRIVE – Part Length from its junction with YABOROUGH DRIVE to its culdesac end
Alternative route: No alternative route
This temporary prohibition is required because works are being or are proposed to be executed on or near the road by FREEDOM GROUP. These works are detailed as delivery and replacement of the substation.
The Order will come into operation on Tuesday, 27 April 2021, and will continue in force for a period not exceeding eighteen months unless extended for a further period by the Secretary of State for Transport, or until completion of the works (whichever is the earlier). The closure is expected to remain in place until Tuesday, 27 April 2021. Definitive dates and times will be notified by on-site advanced warning signs.
The dates and times above are correct at the point of print however implementation on site may vary due to unforeseen circumstances. Diversion routes will be signposted and published online at: One Network – Public Notices and NELC – Public Notices.
A copy of the sealed Temporary Traffic Regulation Order may be inspected online via North East Lincolnshire Council’s Website by searching ‘Temporary TRO’.
For further information, telephone FREEDOM GROUP – 07976836567 for an explanation of the proposals.
Dated this 24/04/2021
Rob G. Walsh – Chief Executive
Municipal Offices, Town Hall Square, Grimsby, DN31 1HU