Menu
Skip to main content

Pavement improvement works begin across North East Lincolnshire

10:31 am, Friday, 31st July 2026 - 2 hours ago

Streets, travel and parking

This year’s pavement slurry seal treatment programme began on Monday 27 July and is expected to be completed by Friday 4 September, subject to weather conditions.

The work involves applying a protective slurry seal treatment to pavements to repair minor defects, improve the walking surface and help prevent water damage. The treatment helps extend the life of pavements and provides a smoother, more even surface for pedestrians.

Slurry surfacing is a cold applied process using a mix of bitumen emulsion, selected aggregates, water and an additive to control the speed of setting. Once laid, the treatment dries quickly and pavements can usually be reopened within 20 to 30 minutes of application, depending on weather conditions. As the works are weather dependent, dates may be subject to change.

Pavement closures

To ensure the safety of both workers and pedestrians, the affected pavement will be closed on the day of the works between 7.30am and 6pm.

Although works may not take the full day to complete, closures will remain in place until the treatment has fully dried and it is safe for public use. The pavement will then be reopened as soon as possible.

Every effort will be made to maintain access to properties whilst works are being carried out, however, there may be short periods when access is restricted. Emergency vehicle access will be maintained at all times.

Planned programme of works

  • Pretymen Crescent, New Waltham – 27 to 31 July
  • Margaret Place, New Waltham – 27 to 31 July
  • David Place, New Waltham – 28 July to 3 August
  • Rutland Drive, New Waltham – 29 July to 4 August
  • Kaymile Close, New Waltham – 29 July to 4 August
  • Charles Avenue, New Waltham – 20 July to 5 August
  • Station Avenue, New Waltham – 3 to 7 August
  • Brunton Way, New Waltham – 4 to 10 August
  • Enfield Avenue, New Waltham – 5 to 11 August
  • Priors Close, New Waltham – 6 to 12 August
  • Waddingham Place, New Waltham – 7 to 13 August
  • B1210 Stallingborough Road, Healing – 10 to 14 August
  • B1210 Great Coates Road, Healing – 10 to 14 August
  • A1173 Riby Road, Stallingborough – 12 to 18 August
  • North Sea Lane, Humberston – 17 to 28 August
  • South View, Humberston – 18 to 24 August
  • Haile Road, Humberston – 19 to 25 August
  • Clee Ness Drive, Humberston – 20 to 26 August
  • Newlands Park, Humberston – 20 to 26 August
  • Townsend Close, Humberston – 20 to 26 August
  • Anthony’s Bank Road, Humberston – 24 to 28 August
  • Kings Road, Cleethorpes – 26 August to 1 September
  • A46, Irby – 1 to 4 September 

Advance warning signs will be displayed on site ahead of the works and will confirm the proposed treatment date.

North East Lincolnshire Council and contractor Kiely Bros apologise for any inconvenience caused and thank residents for their patience while these improvements are carried out.

Next Article
TEMPORARY FOOTPATH CLOSUREPART OF PUBLIC BRIDLEWAY 36 STALLINGBOROUGH, PUBLIC BRIDLEWAY 36 HEALING, PUBLIC BRIDLEWAY 12 GRIMSBY, PUBLIC FOOTPATH 35 STALLINGBOROUGH, PART OF PUBLIC FOOTPATH 46 HEALING, AND PUBLIC FOOTPATH 47 HEALING ORDER 2025 – UPDATE
NOTICE IS HEREBY GIVEN that the North East Lincolnshire Borough Council have made an Order the effect of which will be to close the following Public Rights of Way has...

Share this article