Pavement improvement works begin across North East Lincolnshire

10:31 am, Friday, 31st July 2026 - 2 months ago

Streets, travel and parking

This year’s pavement slurry seal treatment programme began on Monday 27 July and is expected to be completed by Friday 4 September, subject to weather conditions.

The work involves applying a protective slurry seal treatment to pavements to repair minor defects, improve the walking surface and help prevent water damage. The treatment helps extend the life of pavements and provides a smoother, more even surface for pedestrians.

Slurry surfacing is a cold applied process using a mix of bitumen emulsion, selected aggregates, water and an additive to control the speed of setting. Once laid, the treatment dries quickly and pavements can usually be reopened within 20 to 30 minutes of application, depending on weather conditions. As the works are weather dependent, dates may be subject to change.

Pavement closures

To ensure the safety of both workers and pedestrians, the affected pavement will be closed on the day of the works between 7.30am and 6pm.

Although works may not take the full day to complete, closures will remain in place until the treatment has fully dried and it is safe for public use. The pavement will then be reopened as soon as possible.

Every effort will be made to maintain access to properties whilst works are being carried out, however, there may be short periods when access is restricted. Emergency vehicle access will be maintained at all times.

Planned programme of works

  • Pretymen Crescent, New Waltham – 27 to 31 July
  • Margaret Place, New Waltham – 27 to 31 July
  • David Place, New Waltham – 28 July to 3 August
  • Rutland Drive, New Waltham – 29 July to 4 August
  • Kaymile Close, New Waltham – 29 July to 4 August
  • Charles Avenue, New Waltham – 20 July to 5 August
  • Station Avenue, New Waltham – 3 to 7 August
  • Brunton Way, New Waltham – 4 to 10 August
  • Enfield Avenue, New Waltham – 5 to 11 August
  • Priors Close, New Waltham – 6 to 12 August
  • Waddingham Place, New Waltham – 7 to 13 August
  • B1210 Stallingborough Road, Healing – 10 to 14 August
  • B1210 Great Coates Road, Healing – 10 to 14 August
  • A1173 Riby Road, Stallingborough – 12 to 18 August
  • North Sea Lane, Humberston – 17 to 28 August
  • South View, Humberston – 18 to 24 August
  • Haile Road, Humberston – 19 to 25 August
  • Clee Ness Drive, Humberston – 20 to 26 August
  • Newlands Park, Humberston – 20 to 26 August
  • Townsend Close, Humberston – 20 to 26 August
  • Anthony’s Bank Road, Humberston – 24 to 28 August
  • Kings Road, Cleethorpes – 26 August to 1 September
  • A46, Irby – 1 to 4 September 

Advance warning signs will be displayed on site ahead of the works and will confirm the proposed treatment date.

North East Lincolnshire Council and contractor Kiely Bros apologise for any inconvenience caused and thank residents for their patience while these improvements are carried out.

Next Article
Council Leader calls for tougher penalties on utility companies over road disruption
The Leader of North East Lincolnshire Council, Cllr Oliver Freeston, has written to major utility companies calling for greater care and consideration over roadworks and traffic management arrangements. Letters have...

Share this article