Work to improve Cleethorpes Market Place has been on the ground since early summer.
So far, the contractors, CR Reynolds, have been working across Market Place to excavate the existing pavements in several area to install new drainage, and ducts for services, and laying new sub base, before laying the new paving for the scheme.
This is the most disruptive part of the work for local businesses, but some work areas are nearing completion ahead of Christmas.
Pavements outside Sainsburys on Short St, and the southern side of Market Street were completed at the end of last week (Friday 20 November) and reopened to pedestrians. The pavement on Cross Street, is due to be completed today and will also reopen to pedestrians.
New timelines for the work have now been released. Before unexpected items, the project was originally anticipated to be complete in January 2027. This has now moved to mid-March, due to a combination of material challenges and additional work being required to the highway sub-base and drainage system.
Cllr Paul Batson, Portfolio Holder for Housing, Infrastructure and Transport, said: “Since we took over these schemes, we’ve been pressing hard for this to be finished as quickly as possible for the benefit of local businesses and residents.
“Ultimately, as with any project, the weather over the winter may also play a part. We will keep pushing and make sure this project continues at pace.”
In the meantime, to help businesses, changes to car parking in the resort are coming into force. From Monday 7 December, two car parks in Cleethorpes will offer up to one hour of free parking for a two-year trial. The two that will be free for up to 1 hour any time are: Victoria, Cleethorpes – situated behind The Old Vic pub and St. Peter’s Avenue, Cleethorpes (next to Boots).
Additionally, you can park for up to two hours free on weekends and bank holidays at the Civic Offices in Cleethorpes, and also at the Town Hall in Grimsby.
At Market Place, after the next five weeks of work, the contractors will close down for the Christmas period, and work will restart in the new year.
In early new year, work will continue to finish off the new paving to all areas, carry out the works to the roads, install new lighting, hard and soft landscaping, and install all the new street furniture, creating a fantastic public space for people to enjoy all year round.
Find out more about the scheme



Share this article